Background

Agile and SCRUM within Project Driven Creation

Explanation and background article on iterative development methods within the PDC phasing.

In training sessions we are regularly asked how the phasing of Project Driven Creation relates to the Scrum way of working. Our view: sprints belong in the PDC execution phase, with the product backlog as the starting point. But where do you build up that backlog, and where do you lay down the boundaries of the project?

What Scrum does (not) say about it

Scrum describes the product backlog as a dynamic, ordered list that evolves continuously under the responsibility of the Product Owner. The 2020 Scrum Guide added the Product Goal to it as a long-term goal. What Scrum deliberately does not prescribe, however, is how you build up that initial backlog, how you align stakeholders or how you build a business case. Formal boundaries around time, money, quality, information and organisation are also missing from the framework.

Scrum is, after all, deliberately minimal: it leaves open everything that happens before the first sprint. In practice, this gap is filled with additional methods such as Inception sessions, story mapping, product vision workshops or, in scaled frameworks such as SAFe, a Lean Business Case.

Click a part of the image

Where PDC and Scrum reinforce each other

In the PDC definition phase you fill in exactly what Scrum skips. You make the what and why explicit, bring the stakeholders on board and lay down the TMQIOC boundaries in a project contract that has broad support. The output of this phase is a natural source for the Product Goal, the initial backlog and the governance boundaries within which the scrum team can operate autonomously in the execution phase.

This creates a clear division of tasks. With PDC you determine what you make and within which margins; with Scrum you determine how you work towards it iteratively, for part of the project. With Scrum's sprints you thus fill in part of the PDC activity plan. So the methodologies complement each other rather than compete.

Is there nevertheless a 'turf war' between PDC and Scrum in your organisation? We regularly organise in-depth modules building on the PDC training, in which we help optimise the organisation-specific project approach.

Sprint

In the execution phase, the scrum team shapes the development work in successive sprints. A good way of working: use the first sprint to shape the product backlog. That is why this sprint is sometimes called the 0-sprint or inception sprint.