The phases of a project are the main steps in time, from beginning to end. Before and after each phase, you need documents to be able to decide on the next step. With Project Driven Creation, you work on their content together as a project team. An important moment is the Project Startup in the definition phase: in this working session you create a large part of the project contract with the team.
Click on the figure to view in-depth information, resources and templates for each part.
Idea or problem
This is where every task begins, and therefore every project too.
Sometimes the idea or problem originates with the sponsor. Much more often, an expert, user or stakeholder sees the need to improve 'something'. Then determine as quickly as possible who is allowed to decide to spend time, attention and therefore also money on this idea.
There is a good chance that this person will become the sponsor of the project, if it goes ahead. The first phase (the initiation phase) is there to make a decision about that.
Tools for Idea or problem
- ExerciseForces for and against (after Lewin) Exercise: forces for and against pdf (opens in a new tab)
Initiation phase
In many projects this is a messy initial phase, in which it has only just become clear what exactly the problem or idea is. The sponsor has to get to work to arrive at a clear project assignment. In practice, a subject-matter adviser or the intended project manager often does this on behalf of the sponsor. You can use an exploratory, process-oriented approach for this. Make sure the sponsor continues to recognise themselves in the assignment: ultimately, they must be able to stand behind it and give their approval.
Assignment workshop
Is the task still very unclear in the initiation phase? Then an assignment workshop can help you a lot. In this compact working session, the key people involved (sponsor, key stakeholders, intended project manager) clarify the assignment together and decide how they will proceed.
Forms of management other than a project
You will regularly discover in this phase that the task calls for a form of management other than a project, for example a programme or an exploratory process.
Tools for Initiation phase
- ExerciseAssignment workshop Explanation and agenda for the assignment workshop pdf (opens in a new tab)
- BackgroundExploratory process Exploratory process handout pdf (opens in a new tab)
- ExerciseForce field analysis Force field analysis instructions pdf (opens in a new tab)Force field analysis canvas pdf (opens in a new tab)
- ExerciseForces for and against (after Lewin) Exercise: forces for and against pdf (opens in a new tab)
- BackgroundGood sponsorship The sponsor's role: the four A's, the tasks per phase and what working with PDC asks of the sponsor.
- TemplateLetter to the sponsor Letter to the sponsor pdf (opens in a new tab)
- BackgroundOrganising different forms of work Resource for deciding whether a task is a routine, project, programme or process.
- ExerciseWorld café for a project with broad support Exercise: world café pdf (opens in a new tab)
Assignment
The assignment clearly states what the sponsor asks of the project. Formally, the sponsor is its owner. In practice, a project manager or specialist adviser sometimes draws up the assignment. That is fine, as long as the sponsor explicitly supports it and gives their approval.
You may also come across the project assignment as a project brief, briefing, start document, zero document or starting memo. In practice, we often use the project definition template for it.
Tools for Assignment
- ExerciseAssignment workshop Explanation and agenda for the assignment workshop pdf (opens in a new tab)
- ExerciseCollective intake Exercise: collective intake pdf (opens in a new tab)
- BackgroundGood sponsorship The sponsor's role: the four A's, the tasks per phase and what working with PDC asks of the sponsor.
- TemplateLetter to the sponsor Letter to the sponsor pdf (opens in a new tab)
- BackgroundProject definition Explanation of the project definition pdf (opens in a new tab)Project definition template docxProject definition canvas pdf (opens in a new tab)
- ExerciseWorld café for a project with broad support Exercise: world café pdf (opens in a new tab)
Project Startup
A Project Startup (PSU) is a working session with the entire project team. You deliberately take the time to set up the project together and create clarity. Depending on the size, a Project Startup lasts one or more days. For smaller projects, you sometimes see a half-day PSU.
Purpose
In this workshop you work together on the project definition: what is the assignment, which results will we deliver and what falls outside the project? Then, still during the Project Startup, the team builds the activity plan. Together you determine which activities are needed, in what order, within what time frame and who is responsible for what. Because you work out these parts together, you get a shared picture, ownership and a solid starting point for the execution. The sponsor attends as a guest for part of the day.
Agenda
Every PSU is different and calls for a tailored approach. A good intake is essential; you can use the sample agendas as inspiration.
Also inform your sponsor properly about your way of working according to Project Driven Creation. You can use the letter to the sponsor for this.
PDC facilitator
For project managers it is often quite a challenge to facilitate a Project Startup well and, at the same time, help design the content of the project. That is why many organisations invest in PDC facilitators: specially trained process facilitators who know the PDC exercises inside out. They take work off the project manager's hands in designing, preparing and running project meetings such as the PSU. Here you will find more information about PDC facilitators and the training for this role.
Tools for Project Startup
- BackgroundActivity plan Creative structuring step-by-step plan pdf (opens in a new tab)
- ExerciseCollective intake Exercise: collective intake pdf (opens in a new tab)
- TemplateLetter to the sponsor Letter to the sponsor pdf (opens in a new tab)
- TemplatePreparing a Project Startup Project Startup checklist pdf (opens in a new tab)Project meeting design template docx
- BackgroundProject definition Explanation of the project definition pdf (opens in a new tab)Project definition template docxProject definition canvas pdf (opens in a new tab)
- ExerciseProject Startup One-day Project Startup agenda pdf (opens in a new tab)Two-day Project Startup agenda pdf (opens in a new tab)
- ExerciseTeam Spirit Team Spirit: intention for collaboration pdf (opens in a new tab)
Definition phase
In the definition phase, you work out the project assignment into a plan of approach: the project contract. This is the most important phase for setting up your project properly. So put a relatively large amount of attention and effort into it.
At the heart of this phase is the Project Startup (PSU), in which the team shapes the project contract together. The risk analysis is also part of the definition phase. You usually do it after the PSU, in a separate, compact working session. In addition, it can be useful to make a force field analysis.
Tools for Definition phase
- ExerciseForce field analysis Force field analysis instructions pdf (opens in a new tab)Force field analysis canvas pdf (opens in a new tab)
- TemplateLetter to the sponsor Letter to the sponsor pdf (opens in a new tab)
- Entry pointProject contract Project contract template docx
- BackgroundProject definition Explanation of the project definition pdf (opens in a new tab)Project definition template docxProject definition canvas pdf (opens in a new tab)
- BackgroundProject planning in 7 steps From activity plan to schedule: seven steps, from dependencies and milestones to monitoring progress.
- ExerciseProject Startup One-day Project Startup agenda pdf (opens in a new tab)Two-day Project Startup agenda pdf (opens in a new tab)
- TemplateQuality table Quality table template docx
- ExerciseRisk analysis and risk management Risk analysis step-by-step plan pdf (opens in a new tab)
- BackgroundStakeholder analysis: which method do you choose? Stakeholder analysis methods: overview pdf (opens in a new tab)
Project contract
In the project contract you record the agreements you use to steer the project: what you will do, within which boundaries, and how you will work together – both with the sponsor and with each other. See it as a real deal, a psychological contract.
Tools for Project contract
- TemplateCommunication plan Communication plan template docx
- Entry pointProject contract Project contract template docx
- BackgroundProject definition Explanation of the project definition pdf (opens in a new tab)Project definition template docxProject definition canvas pdf (opens in a new tab)
Execution phase
In the execution phase, the team does the work: you carry out the tasks and activities and in this way achieve the results and subdeliverables. Depending on the content, you often divide the execution into content-related sub-phases. The execution of an IT project, for example, looks very different from that of a construction project.
Does the execution take a long time (rule of thumb: more than 4–5 months)? Then organise a project fresh-up. In this compact working session, a follow-up to the PSU, the team carries out an interim evaluation and refines the activity plan for the next phase. In longer projects, you often do this several times.
Inform the sponsor and the key stakeholders regularly about progress during the execution. Many organisations use progress reports for this. Our advice: keep them simple and clear.
Tools for Execution phase
- BackgroundAgile and SCRUM within Project Driven Creation Article: Agile and PDC pdf, in Dutch (opens in a new tab)
- ExerciseDiscussing commitment Exercise: discussing commitment pdf (opens in a new tab)
- TemplateProgress report Progress report template docx
- ExerciseThe project fresh-up Exercise: project fresh-up pdf (opens in a new tab)
Results
In every project there comes the moment when you have delivered all the results from the project contract. This is often a symbolic moment, because the actual delivery consists mainly of subdeliverables that you complete along the way during the execution phase. Do you want a predictable project? Then describe those subdeliverables properly in the definition phase.
Make sure the substantive work is really finished at this moment. Does the project assignment include things such as revisions, adjustments, follow-through or implementation work? Then carry these out in the last sub-phase of the execution.
Tools for Results
- BackgroundClosing a project What happens once the result has been delivered: handover, evaluation and formally closing the project.
- TemplateQuality table Quality table template docx
Closure phase
In this compact phase you close the project neatly. You often still do some administrative work, such as making a final overview of the hours and budget spent. In addition, by all means celebrate the successful completion with a party. It is good practice for the sponsor to formally end the assignment of the project team (and therefore also of the project manager). In project management jargon, this is called: granting discharge.
Close your project with a final evaluation: that is both professional and useful.
Tools for Closure phase
- BackgroundClosing a project What happens once the result has been delivered: handover, evaluation and formally closing the project.
- ExerciseEvaluation Explanation for facilitators: evaluating with the lemniscate pdf (opens in a new tab)Exercise: project evaluation – the session in seven steps pdf (opens in a new tab)Article: Evaluating is looking ahead pdf, in Dutch (opens in a new tab)
Evaluation
Evaluate your project regularly. In the phase overview, the evaluation is drawn at the end, but evaluate at interim stages too: then you can adjust course.
Involve the whole team in the project evaluation and pay attention to all four dimensions of project success.
Tools for Evaluation
- BackgroundClosing a project What happens once the result has been delivered: handover, evaluation and formally closing the project.
- ExerciseDiscussing commitment Exercise: discussing commitment pdf (opens in a new tab)
- ExerciseEvaluation Explanation for facilitators: evaluating with the lemniscate pdf (opens in a new tab)Exercise: project evaluation – the session in seven steps pdf (opens in a new tab)Article: Evaluating is looking ahead pdf, in Dutch (opens in a new tab)
- Entry pointSuccess factors Four dimensions that determine the success of your project.
- ExerciseThe project fresh-up Exercise: project fresh-up pdf (opens in a new tab)