A project fresh-up, also called a project follow-up (PFU), is a working meeting in which the project team shapes the next phase of the project.
In short
- Purpose:
- Evaluating. What is going well, what could be better? Establish together how the project is going and discuss what you will do to make it go (even) better.
- Contracting again. Make sure everyone involved can take shared ownership of the coming phase: team members, sponsor and project manager. If the team, the sponsor or the project manager changes, you will need to contract again in any case.
- Concrete agreements for the next phase. Make the activity plan for the coming phase concrete, including the schedule and the division of tasks.
- When: as an interim meeting in the execution phase. Rule of thumb: if execution takes longer than four to five months, it is wise to organise one. In longer projects you often organise several.
- With whom:
- The project team in any case. Think especially of new team members you need in the next phase, and of team members who are leaving: with them you discuss the evaluation and lessons learned, and you thank them for their efforts.
- The sponsor, optionally, for all or part of the meeting, to discuss the points of attention for the coming phase.
- Experts or advisers, optionally, who can think along about the next phase.
- A delegation of end users, optionally, to hear their wishes and experiences.
- Optionally (recommended), a process facilitator. Do yourself a favour as project manager and let someone else facilitate the meeting. Then your hands are free to think and work along.
- How long: half a day to a full day, depending on the complexity of the project and the issues at play.
How to go about it
A possible set-up:
- Welcome and purpose of the meeting by the project manager; explanation of the programme by the process facilitator.
- Check-in. Ask all participants when the meeting will be a success for them and what they need to take part. For example with scaling questions.
- Looking back and looking ahead. Evaluate, using the four dimensions of project success, how the project is going and what you want to do to make it go better. See Evaluation. End with concrete agreements for the coming phase.
- Sharpening the project definition for the next phase. Check with the team in particular the subdeliverables to be delivered in the coming phase, the scope demarcation (what not yet), the constraints (lead time, money, hours and quality requirements) and the users: which ones, and how do you involve them in this phase?
- Making the activity plan for the coming phase. List the activities with the creative structuring exercise and put them on the timeline. See Activity plan.
- Agreements for follow-up. Who works out what, and how will the project meetings continue?
- Closing, optionally with the sponsor, to discuss your actions and any questions or concerns.
Other emphases
You can also give certain aspects more attention:
- If the project environment needs more attention, do a force field analysis with the team.
- Are there many disruptions? Then a risk analysis is a good starting point: with it, you plan the activities for the coming period with more focus, to prevent those disruptions.
Related tools
ExerciseProject StartupWhat a Project Startup is, how to prepare it and what it consists of, with sample agendas of one or two days.ExerciseEvaluationExplanation, questionnaire and exercise for evaluating projects, also along the way, with the PDC success factors.BackgroundActivity planOverview of the components of the activity plan, with the step-by-step plan for the creative structuring exercise.