The force field analysis is a form of risk analysis for a project. You focus on the attitude of the people involved and on their relationships with each other, and therefore less on substantive considerations and business setbacks. You often already know the risks in those attitudes and relationships without being aware of it, and you are already dealing with them. With this exercise you quickly get a clear picture of them, and then you can also discuss them more easily.
You map everyone involved on a project map with four quadrants. With a colour you indicate how you perceive their attitude towards the project: positive, ambivalent or neutral, negative or unknown. The more important a person involved is to the project, the closer to the centre you place them. Then you map the relationships between them and discuss which risks you see and what you will do about them.
In short
- Purpose:
- Getting a view of everyone involved in the project. That alone is often valuable.
- Showing quickly and clearly where the friction is: the risks that lie in the people involved, their attitude and their relationships with each other.
- Making a plan to avoid, reduce or transfer those risks.
- When: in the initiation phase and the definition phase, for example as part of a Project Startup or in the feedback session of an assignment workshop. If the environment needs more attention later in the project, you can also make one then, for example at a project fresh-up. Do not do it just once: analyse the force field regularly and intervene where necessary.
- With whom: you make the analysis yourself, as project manager, or together with team members. You can read how to go about it with a team below, under With a team.
- How long: our sample agenda for a two-day Project Startup allows an hour for it, plus an hour to discuss the risks and actions in plenary.
- What you need: a sheet on which you draw the project map, or the force field analysis canvas (opens in a new tab), and markers in four colours: green, orange, red and black. If you work with a team, you also need sticky notes.
How to go about it
You can do a force field analysis with a team in all kinds of ways, from a physical constellation with figurines to a drawing you make together. In preparation, it is useful to know the basic PDC exercise well. The instructions (opens in a new tab) contain this step-by-step plan, with an example of a completed project map. You use the canvas (opens in a new tab) to make the analysis yourself or together with team members.
- Draw the lines of the project map on a sheet, with the task – the project – in the centre. Divide the sheet into four quadrants:
- Users: have to do something with the project result, benefit from it or are inconvenienced by it: clients, works councils, target group, etc.
- Strategy: those with final responsibility for the project: funder, sponsor and delegated sponsor.
- Execution: team members and third parties with whom concrete agreements have been made about what they will deliver: consultants, draughtspeople, printers and specialists.
- Suppliers: mainly staff deployment: line managers, staff managers, direct superior.
- Make a list of everyone involved in the project or programme. People can be involved in various roles. If you like, use the four quadrants above as a source of inspiration to think about the people involved in each quadrant.
Tip: try to use the names of the people involved as much as possible, rather than the ‘party’ or the part of the organisation. - Examine the attitude and behaviour of the people involved. Use a colour and a smiley to show how you perceive the attitude of each person involved towards your project or programme:
- Green: positive, engaged attitude
- Orange: ambivalent or neutral
- Red: negative or even obstructive
- Black: unknown
- Place the people involved on the project map.
Note: people involved can have a role in several areas (wear several hats) and sometimes even have a different attitude towards the project, depending on the hat they are wearing.
Tip: you can indicate how important the people involved are for the project by placing them closer to the centre. The further away from the centre, the less important. - Show the relationships between the people involved. Draw lines between the most important relationships in the force field. Indicate what each relationship is like:
- Green: positive, good relationship
- Orange: some tension in the relationship
- Red: tensions between these people
- Black: unknown
- Identify the risks. Think about and discuss which risks you perceive in the force field.
Note: question marks in a force field can also be a risk. - Make a plan. Think about and discuss what you can do about these risks to avoid, reduce or transfer them. Think of extra activities, strengthening your communication plan, adjusting the schedule, changing the team composition or the scope, finding another sponsor or even stopping the project. Record the measures in a table with Risk, Measures (activities), Who? and When?, just as in the risk analysis.
Tip: make sure you formulate concrete actions and assign an owner.
An example of such a table:
| Risk | Measures | Who | When |
|---|---|---|---|
| Director X has concerns. | Arrange a conversation. | … | … |
| The works council has a lot of questions. | Invite a few works council members to a meeting. | … | … |
| Little is happening in department B. | Join the department meeting. | … | … |
With a team
- Ask all team members to bring a list of everyone they know to be involved in the project.
- During the meeting, complete the list together. Write the names on sticky notes and discuss the attitude of each person involved straight away. Add a coloured smiley, or choose a colour of sticky note that matches that person’s attitude.
- Have a small group (two or three people) place all the sticky notes on the flip chart.
- Check with the team: do they recognise the picture?
- Discuss with the team where they see risks in the relationships between the people involved: the red lines.
- Then discuss the relationships that offer opportunities: the green lines.
- Make a list of the risks and divide them among pairs of team members. Ask each pair to propose measures to limit or resolve the risk.
Variant: the force field as preparation
- Ask each team member to make a force field in advance, as preparation.
- At the meeting, have the team members first discuss their analyses in pairs and merge them into one analysis.
- Then have two pairs at a time form a group of four. Each group of four merges its two analyses into one force field analysis.
- Have the groups of four present their analyses to each other.
- Then form groups that come up with measures together.
Which analysis do you choose?
With the force field analysis you relate everyone involved to the task and to each other, weighing both the people involved and their relationships with each other. This also lets you devise strategies via other people involved. Other questions about stakeholders call for other methods; you will find them in the overview under Stakeholder analysis. Forces for and against is a different model: there you weigh the forces for and against a single proposal.
Tips
- Simply listing everyone involved can give you new insights.
- If you work with a team, you can discuss the attitude of the people involved in subgroups and then discuss the risks and actions in plenary. You can read how to go about this above, under With a team and in the variant.
- Add the actions to the schedule.