In the initiation phase, the sponsor is responsible for a sharply formulated project assignment that has broad support. That is often not an easy task, especially if the project concerns complex matters in which several players are involved. The sponsor must be able to instruct the project team as well as possible about WHAT he or she expects of them. The better the WHAT is put into words, the better the team can come up with proposals about the HOW.
That is what the assignment workshop is for: an interactive workshop in which a group of people involved help the sponsor and the project team to define the project as well as possible. With a half-day meeting, and a feedback session a week later, you make a realistic investment when it comes to a complex project of a year or more.
In short
- Purpose: gathering the input with which the sponsor, with or without the help of the intended project manager, can formulate a project assignment that has broad support. All nine components of the project definition are worked out in it from the sponsor’s perspective.
- When: in the initiation phase, prior to the Project Startup, when the task is still very unclear. If it is clear from the start that the main focus is getting the assignment clear, call the meeting an assignment workshop rather than a Project Startup. That way you prevent the term Project Startup from losing its meaning.
- With whom: a group of no more than twelve people involved and possibly a process facilitator; see below.
- How long: half a day, with a feedback session a week later.
- What you need: flip charts for the work in subgroups.
Participants
To keep the meeting workable, we recommend inviting a group of no more than twelve participants. If you want to work with a larger group, choose other exercises, for example a world café. Possible participants are:
- the sponsor;
- intended members of the steering committee;
- representatives of the user group (“What we really need is…” “What we really don’t need is…”);
- key specialists who can formulate constraints, for example for the quality of the end result (“What it has to comply with is…” “What you need to watch out for is…”);
- representatives of supplying business units (“Take into account these other projects, programmes and activities…” “Be aware that our schedule for the coming period looks like this…”);
- the intended project manager (handy with a view to the handover);
- a process facilitator (can be useful, especially if there are conflicting interests).
How to go about it
The explanation and the agenda are also in the download Explanation and agenda for the assignment workshop (opens in a new tab).
The workshop: an agenda for half a day
The agenda could look like this, assuming half a day with twelve people and a process facilitator:
- Welcome and objective. The sponsor welcomes everyone and explains the objective of the workshop. The process facilitator explains the programme.
- Check-in: in which roles are you here, when is this workshop a success for you and what do you need to take part in it?
- The task, for example with the exercise ‘the TV report’: In two years’ time, a camera crew will visit us to make a TV report about the result of our project. They have heard that an outstanding achievement has been delivered here. In the report, we may show five unique parts of the result. Split up into three mixed groups of four and come up with a proposal for the five scenes you want to show. In other words: what will we have achieved when the project is finished, and what are its most essential elements? Each group gives a short presentation.
- Elaboration in subgroups: the subgroups make proposals on flip charts for objectives and the main results as well as the scope demarcation. That way you eventually arrive at a specification of the ‘must haves’, ‘need to haves’ and ‘nice to haves’. Put these side by side in plenary, discuss the main differences and make a decision.
- Constraints conversation: with the intended result in view, it is good to have a conversation about the constraints. What else would those present like to pass on to the sponsor when it comes to the constraints and the process of the project? What does the sponsor need to take into account? What is minimally necessary, who needs to be involved?
- Closing and check-out.
A week later: the feedback session
- Work out the session. The intended project manager works out the session in a draft project assignment.
- Discuss the draft with the group. After a week, the group meets again to discuss the draft and add to it. In this session you can address matters such as:
- additional input or afterthoughts;
- a force field analysis and/or risk analysis;
- information about next steps, including schedule and communication (initiation phase, transition to the definition phase and the Project Startup, expected start of the execution phase and so on).