Exercise

Project Startup

What a Project Startup is, how to prepare it and what it consists of, with sample agendas of one or two days.

A Project Startup (PSU) is a joint working session with the whole project team: a working conference, not a kick-off. You deliberately take the time to set up the project together and create clarity. The team works on the project definition and builds the activity plan together. Ideally, the sponsor joins as a guest for part of the day.

In Project Driven Creation, we assume that you achieve more success if the team shapes the approach and structure of the project together as much as possible. There is most room for this at the start of the project. The PSU is therefore the central moment in the definition phase. This is where you and the team create a large part of the content of the project contract. Doing this together creates a shared picture, ownership and a solid starting point for the execution.

In short

  • Purpose: setting up the project together: what will we deliver, what falls outside it, which activities are needed and who does what? The most important outcome is that the project comes alive, that participants know all the ins and outs and want to go for it.
  • When: in the definition phase, once the assignment is in place.
  • With whom: the whole project team, guided by a (PDC) facilitator. The sponsor joins as a guest for part of the day, at least for the collective intake.
  • How long: depending on the size of the project, a whole day to several days; for smaller projects sometimes half a day.
  • What you need: a room with movable furniture and walls you can stick things on, flip chart sheets, sticky notes and markers, and project information to display for inspiration.

How to go about it

Beforehand

  1. Check whether a Project Startup is the right meeting. If it is clear from the start that the main focus is getting the assignment and the project definition clear, organise an assignment workshop and call the meeting that too. That way you prevent the term Project Startup from losing its meaning.
  2. Inform the sponsor about your way of working according to Project Driven Creation and what it asks of him or her, for example with the letter to the sponsor.
  3. Hold an intake and make a meeting design. Every PSU is different, and a good intake is very important. Use Preparing a Project Startup, with the checklist for the intake and the meeting design template.

On the day itself

These parts come from our sample agenda for a one-day PSU.

  1. Start. The project manager or sponsor welcomes everyone. The facilitator explains the programme and the purpose. The participants check in and get to know each other, for example with scaling questions. With Team Spirit they make agreements about the atmosphere. You can also hold a round of Concerns and Commitments: what are you concerned about and what are you looking forward to?
  2. Collective intake with the sponsor on the importance of the project and its urgency, with a round of questions and answers. See Collective intake.
  3. Work on the project definition. The team works out (in subgroups) the components of the project definition, checks whether it is complete, discusses questions and concerns and reports back to the sponsor.
  4. Build the activity plan together using creative structuring. Discuss coherence and completeness, and have everyone sign up for activities. See Activity plan.
  5. Make agreements on further elaboration and the next steps. Who will record it, and in which template? What does the project manager still need from the team members? A common agreement is that everyone estimates the hours for their own tasks. And when will you meet again, for example for the risk analysis? Also take a moment to celebrate that the team has reached an important milestone.

In a two-day PSU, the first day is usually almost the same as a one-day PSU. On the second day there is time for the schedule as a whole and the milestones, a force field analysis, a presentation to the sponsor and agreements on organisation and information. If the project definition requires a lot of work in subgroups, the morning programme of the one-day PSU can take up a whole day. The second day is then mainly spent on the activity plans, which will then be more extensive.

Depending on the purpose, you can also include other parts, such as a stakeholder analysis, a communication plan or a description of the project organisation.

Afterwards

  1. Work out the results in the project contract. You close the definition phase by adopting and signing it.
  2. Plan a separate risk analysis, preferably a week or two later. By then participants have been able to digest the results and the plan.
  3. If the execution takes longer (rule of thumb: more than four to five months), organise a project fresh-up to evaluate along the way and sharpen the activity plan for the next phase.

Tips

  • Facilitating a PSU while also contributing to the content is often quite a challenge for project managers. That is why many organisations work with PDC facilitators. You will find tips for the start and for difficult situations under Facilitating project meetings.
  • Evaluate the PSU itself as well, for example with the questions for the I side under Discussing commitment.

Sample agendas

Every PSU is different, and a good intake is very important for a successful meeting. Still, it can help to consult an example. Below you will find sample agendas for a one-day and a two-day Project Startup. You can shorten the one-day agenda to half a day; you can extend the two-day agenda further.