"Stakeholder analysis" is not one resource but a family of methods. They differ mainly in the question they answer. Online and in books on facilitation methods you will find a great many resources. Below you will find four common practical questions, with examples of methods that fit them. There are more useful methods that lead to the same insight.
Analysis is not yet management
The terms stakeholder analysis and stakeholder management are often used interchangeably. Yet there is a fundamental difference. Stakeholder management is about dealing with the risks that arise from the interests of stakeholders. It is therefore a specific approach to risk management.
In practice, the analysis is often made, but the step to conclusions and actions is missing. Then there is no longer any management. So agree on clear follow-up actions, with an owner and a deadline.
Four questions, and the method that fits
| Question | Method | What it gives you |
|---|---|---|
| Who actually are the stakeholders? (identifying and delimiting) | Stakeholder brainstorm or stakeholder register | All people involved, collected and recorded in a structured way. You cannot analyse what you have not mapped. |
| Onion model | Stakeholders in rings, from inside to outside: project team, (internal) organisation, external stakeholders, wider environment. This helps you decide who is inside and who is outside. | |
| How important is who? (prioritising) | Power/interest grid (Mendelow) | A quick prioritisation by power (influence) and interest; it says nothing about attitude or relationships. |
| Power/predictability matrix | Prioritisation by influence and by how predictable or desirable the behaviour is. | |
| Stakeholder Salience Model | A finer prioritisation by power, urgency and legitimacy, with seven types of stakeholders. | |
| What do they think of it, and where do they need to go? (attitude and engagement) | Attitude analysis | Influence and attitude (for, against or neutral) per stakeholder: four types, from support to risk. |
| Stakeholder Engagement Assessment Matrix | Current and desired engagement per stakeholder; this gives direction to the follow-up actions. | |
| How do they relate to each other? (relationships and network) | Force field analysis (PDC) | All actors in relation to the task and to each other, weighing both the stakeholders and their mutual relationships. This lets you devise strategies via other stakeholders too. |
How do you choose?
The choice mainly depends on the type of task and the insight you need to determine the right follow-up actions. In practice you usually use several methods one after another:
- First identify (stakeholder register, onion model).
- Then prioritise (power/interest grid or, if needed, the salience model).
- Then go deeper: into attitude or relationships.
What you do with it, you record in your risk analysis and your communication plan.