Are you facilitating a Project Startup or another project meeting? Then you need good preparation. Plan an intake with the project manager and any other people involved well in advance, so that you get a good picture of the purpose and nature of the meeting.
Intake with whom?
Of course you talk to the project manager: he or she is your client as a facilitator. But it can also be good to talk to the sponsor of the project.
Purpose of the meeting
First discuss what they want to achieve: which objectives have priority and what is feasible in the meeting? A Project Startup can serve several purposes:
- support for and understanding of the project;
- clarity about the assignment and the scope demarcation;
- getting acquainted and building trust;
- a shared approach;
- cooperation and shared responsibility;
- a quick start or acceleration of the project;
- insight into risks and possible measures;
- a shared experience and common insights among all participants and the sponsor;
- working agreements for the collaboration and the first phase.
Depending on the phase, specific objectives may need more attention: specifying the project results and the work needed for them, agreeing on the relationship with users and other stakeholders, making a schedule and capacity estimate, team building, exploring the environment and the force field, or arranging the budget.
Note: if it is clear from the start that the main focus is getting the assignment clear, give the meeting a different title, for example assignment workshop. That way you prevent people from thinking that a Project Startup is only about the assignment.
Possible results
Also agree on the concrete results and on the form in which they will be recorded. Possible results:
- a project definition with broad support and a clear scope demarcation;
- a worked-out activity plan for the phase concerned;
- agreements on tasks, authorities and roles;
- a list of agreements, each with a deadline and a person responsible;
- agreements on working together, dealing with differences of opinion and conflicts, and decision making about them;
- a force field analysis with an action plan.
A risk analysis can also be part of the Project Startup, but we recommend a separate meeting, preferably a week or two later. By then participants have been able to digest the results and the plan, and are ready to face the risks.
The most important outcome, of course, is that the project comes alive, that participants know all the ins and outs and want to go for it.
Checklist for the intake
The download contains the complete checklist. The topics:
- The group: who is needed in which role, what is the level of knowledge, do participants know each other, what does this group need?
- Project content: how did it come about, what are the objectives, which phase is it in, who is involved, which decisions have been made, which documents and visual material are available?
- Sponsor: how does the sponsor feel about it, how committed is he or she, what does the sponsor find important?
- The project manager: how does he or she feel about it, what type is he or she, which role does he or she want to take?
- Expectations of the facilitator: what does the project manager expect of you?
- Your own assessment: when do you say yes to the assignment, and what do you need?
- Room: location, logistics, materials and project information to put on display.
- Information: list of participants, who makes the programme, who sends the invitation, who takes notes and photos?
At the end of the intake, check your first picture with the people you spoke to: the purpose, the outline agenda and the intended results.
The meeting design
Based on the intake, make an extensive and workable meeting design for yourself. It gives you something to hold on to, but you can also let go of it when the situation calls for it.
The design template has two parts:
- At the top the meeting (name, date and time, number of participants, location and setting), the goal (goal of the meeting, preferred behaviour of participants) and the group (group characteristics, expected behaviour and risks).
- Below that the programme, with for each item: time, subject, result, method, who and what is required.
For the content of the programme, see the sample agendas under Project Startup.