Exercise

Discussing commitment

Exercise for discussing the personal commitment of team members during an evaluation, without assigning blame.

The commitment of everyone involved is one of the most important factors for completing a project successfully and with enjoyment. Yet there are often good reasons why team members do not commit fully. With this exercise you discuss this without assigning blame, as part of an evaluation.

In short

  • Purpose: learning together from the past phase and identifying the lessons and points for improvement for the coming phase or future projects, and, in doing so, discussing personal commitment without assigning blame.
  • When: at an interim evaluation of the past phase or at the end of the project.
  • With whom: the whole project team. Preferably ask a process facilitator, such as a PDC facilitator, to guide the meeting. As project manager you can then take part yourself; after all, you are part of the team too.
  • How long: set aside an hour for it.
  • What you need: a large sheet or flip charts, thick markers in different colours and round stickers.

What is commitment?

Someone has commitment when he or she wants to contribute (motivation), is able to contribute (qualities) and has the room to do so (time). It is only natural that this does not always fully work out.

In Project Driven Creation, commitment means involvement and taking responsibility. Everyone involved feels like a co-owner of the project. The key question is: can you connect the project to what matters to you?

Why this belongs to the I side

Among the success factors, the I side is about commitment: does everyone come into their own, and is everyone willing and able to take responsibility for the project? In the evaluation lemniscate, the I side includes personal leadership, commitment and steering. If you neglect this side, people make individual choices about their contribution to the project that are not necessarily good for the project as a whole.

How to go about it

  1. Start with a good check-in. Evaluating can feel vulnerable. Explain the purpose: learning together from the past phase and improving the approach for the next phase or the next project. Agree on the atmosphere, for example with Team Spirit. Here it is especially important that everyone speaks openly.
  2. Explain what commitment is. It is about wanting, being able and having the room. Together you explore how things stood with commitment in the different phases, and how it could have been better.
  3. Draw the graphs. Put up a large sheet and draw two axes: horizontally the period you are evaluating, vertically the commitment. Everyone draws their own line with a thick marker.
    Tip: ask everyone to really do this for themselves and not to respond to each other yet.
  4. Discuss the results. Start with a general round: what strikes you? Then look at each line separately. Encourage the others to keep asking questions with curiosity, and refer to the agreements on the atmosphere if needed.
    Tip: first ask the others what they are most curious about. This helps the person presenting to focus their story.
  5. Prioritise and choose. Give everyone a few round stickers to place on the parts of the graphs the team wants to draw lessons or improvements from.
  6. Formulate lessons and improvements. Do this in pairs or small groups, concisely and legibly on flip charts or large sticky notes. The more concrete the better: who does what and when?
    Tip: sometimes it turns out that two team members or part of the team still need to discuss something with each other. Make room for this in your programme.
  7. Discuss the proposals. Each group explains its proposals and the team adds to them. Make sure the proposals are concrete and end up where people will use them in practice. Otherwise they all too often disappear into a folder, never to be found again. Where possible, take a decision on the proposals.

Questions for the I side

We use these questions when evaluating a Project Startup. They also help in step 4.

  • When did you use your personal qualities?
  • What gave you the most satisfaction?
  • Where did energy leak away? When was it hard going?
  • To what extent do you feel like a co-owner of the project?

Statements for the I side

If you want to evaluate the I side more broadly, you can use these statements.

Theme Statement
Choice The project manager and team members could choose for themselves which work they contribute to, and were encouraged and challenged to do so.
Creativity The project manager and team members were given plenty of room to shape the project approach themselves.
Expertise There was attention and room for developing the project manager, support staff and team members in project management.
Commitment We took the commitment of everyone directly involved seriously and regularly asked each other about it.
Reciprocity There was attention and room for the professional and personal development of the team members.
Escalating The project manager and other leads did not muddle on when problems arose, but asked for help in time and escalated when needed.
Project manager The project manager knows his or her own qualities and limitations, is strong, commands respect from sponsors, line managers and team members, and actively maintains equal relationships with them.

See also Evaluation for an evaluation of all four groups of success factors.

Related tools