Once you have built the activity plan, you make the schedule. You work it out in seven steps. Then include an overview of the interim results and the planned delivery date in the project contract. You report on this to the sponsor and stakeholders in the progress report.
The seven steps
- Determine the dependencies between the activities. A PERT chart is a useful resource for this.
- Name milestones. In creative structuring you put milestones and important consultation moments with the team and the sponsor on the timeline, so you can schedule them in time.
- Estimate for each activity how much time it will take. Let the people who do the work make the estimate, and learn from evaluations and earlier experience. The risk is that an estimate is not sufficiently substantiated. Build in margins. A common agreement after a Project Startup is that team members estimate how many hours they need for their own tasks.
- Align with the team members' calendars. Record the schedule in the calendars, consider forward planning versus backward planning, and check the commitment to the schedule.
- Determine the total lead time: the critical path.
- Compare the schedule with the agreed constraints. Time is one of the constraints in the project definition: is there a final deadline?
- Monitor progress. For example with a bar chart.
Planning together
The schedule does not have to be the project manager's work alone. In creative structuring team members first adopt activities themselves. Then, in small groups of two or three, they make the schedule: they put their own sticky notes in order, add missing activities and place them on the timeline to form a bar chart. That way team members can take their own calendars into account. Then the team looks at dependencies, moves things where needed, and determines the milestones.
Tip: most teams cannot plan much further ahead than six to nine months. So focus on the coming period.
Does the project need to go faster?
If the schedule does not fit within the agreed time, you have a few options:
- adjust the scope and/or the quality;
- work longer days;
- deploy more capacity or replace people;
- organise the project process differently, with shorter lines of communication;
- postpone or drop activities; this increases the risk.