Progress report

Fillable template for a simple progress report for the project.

Keep the sponsor and the most important stakeholders regularly informed about progress during the execution. Many organisations use progress reports for this. Our advice: keep them simple and clear.

You can use this fillable template for that. It contains a summary of the project status for schedule, budget and quality (green, amber or red), a description of the progress and the (interim) results achieved.

Why report?

In the execution phase, the project manager monitors progress and the sponsor checks it. In this phase the sponsor's tasks also include making go/no-go decisions, assessing the results and checking the accountability for time and money; see good sponsorship. With a progress report you give the sponsor (and the most important stakeholders) that information in a consistent way.

What does it contain?

  • Project and period
  • Summary of the project status: overall, schedule, budget and quality, each green, amber or red
  • General description of progress
  • (Interim) results achieved
  • Risks and measures
  • Budget spent and an estimate of the budget until delivery
  • Expected interim results in the next period and the expected delivery date of the project
  • Other comments

The basis: the project contract

Include an overview of the interim results and the planned delivery date in the project contract. You report on these in the progress report. The project contract is also the basis for the other parts of the template:

  • Schedule: the interim results and milestones from the schedule. You monitor progress with a bar chart, for example; see step 7 of project planning in 7 steps.
  • Budget: the project budget, in money and/or hours.
  • Quality: the quality requirements, possibly worked out in a quality table.
  • Risks and measures: the risks and measures from the risk analysis, for which the team makes agreements about recording and follow-up.

Tips

  • Agree in advance on the frequency and form of the reports. Then report on progress systematically, effectively and unambiguously.
  • Keep the schedule up to date at all times and keep track of spending against the budget.
  • Give drawing up the reports a place in the activity plan, in a Project management cluster, and put the meetings with the sponsor on the timeline. That way you can schedule them in good time.

Looking back

In an evaluation you can assess the reporting with the statement on reporting under IT (structure); see Evaluation.