The sponsor represents the strategic system and is the direct point of contact for the project manager. The sponsor decides on starting, stopping and changing the project.
The four A's of a good sponsor
What can you, as project manager, expect from your sponsor? We sum it up in four words that begin with an A:
- Authorised. The sponsor must be able to decide on the direction of the project within set boundaries, on behalf of all the managers and other officials involved in the strategic system. Sometimes the sponsor does need to consult other managers to do so. A good steering committee can help with this.
- Able. The sponsor knows what he or she is allowed to decide on and makes sure decisions are made swiftly, so that the project can move forward. This requires the sponsor to be able to chair meetings, facilitate decision making, and sense and manage the force field.
- Available. When there are urgent issues, you as project manager must be able to contact your sponsor quickly. The higher up the hierarchy, the less available a sponsor often is. The sponsor must also lend a listening ear to the issues in the project.
- Attached. The sponsor represents the users of the result and should therefore also lose sleep if the project is not going well. He or she will have to use their contacts and role to protect the project, and is an important ambassador for the project.
Commissioning in two steps
If you work with Project Driven Creation, the sponsor preferably commissions the project in two steps. First for the definition phase, in which the team and the sponsor get a sharp picture of what the project involves. At the end of that phase there is a project contract: a well-considered and broadly supported plan. With that, the sponsor commissions the execution.
This approach asks three things of the sponsor:
- Patience. Execution does not start straight away; first comes the Project Startup. You easily make up for that time, because along the way you lose no energy to misunderstandings, resistance, avoidable risks and mistakes.
- Their own time. In the definition phase the sponsor invests more time than he or she may be used to. The sponsor is at least a guest at the Project Startup, for the collective intake: a conversation with the team about expectations, objectives, intended results and constraints.
- Room to stop. Because the team thinks things through thoroughly in the definition phase, it may turn out that the project is not viable. Better to turn back halfway than to go astray altogether: that insight costs much less at the start than halfway through.
Use the letter to the sponsor to explain this way of working.
Tasks of the sponsor per phase
| Phase | Tasks of the sponsor |
|---|---|
| Initiation phase | Initiating the project. Selecting the project manager and holding exploratory talks with him or her. Building support. Finding out whether people and resources are available. Assessing the draft composition of the team. |
| Definition phase | Attending (part of) the Project Startup. Assessing drafts of the project contract. Making people and resources available. Setting up governance structures, such as a steering committee. Approving the project contract. |
| Execution phase | Monitoring progress. Making go/no-go decisions. Supporting the project manager and the team. Protecting the project. Assessing the results. Checking the accountability for time and money. |
| Closure phase | (Having) the result implemented. Assessing the performance of the project manager. Discharging the project manager and the team. |
Delegated sponsor
Sometimes the sponsor delegates the role. A delegated sponsor works well if he or she has the trust of both the sponsor and the project manager, has a clear mandate and acts effectively.
The steering committee
A steering committee is a regular meeting in which the sponsor can consult the most important decision makers. You only need one if the sponsor does not already see those decision makers regularly in other meetings. In collaborations between organisations a steering committee is often essential.
- A steering committee is not a democracy: the sponsor remains ultimately responsible, has the final say and chairs the meeting.
- The steering committee advises the sponsor. Make clear agreements about its role and about decision making, and make sure the user is represented.
- Choose an odd number of members and work without substitutes.
- The project manager is a guest and not a decision-making member; he or she often acts as secretary.
Looking back
In an evaluation you can assess sponsorship with the statement on sponsorship in the evaluation.