Quality table

Template for recording in advance, per result, when it is good enough: criteria, standard and measuring instrument.

For many projects it is useful to make explicit when the results and subdeliverables are good enough. Work this out together with the team members, so that everyone in the project team has the same picture. A quality table helps with this.

What the table looks like

For each result you record which criteria it must meet, which standard goes with them and which measuring instrument you use to test this. An example:

Result Criteria Standard Measuring instrument
Report Compact size Fewer than 10 pages Counting
Readable for laypeople Test readers give readability at least a 7 out of 10 Test reading by a number of test readers
Clear structure In line with our templates and standards for advisory reports Review by the communication adviser

What goes in the columns?

  • Result: the result or subdeliverable as described in the project definition.
  • Criteria: the characteristics the result must meet.
  • Standard: the value the criterion must meet. Words like 'original', 'user-friendly' or 'safe' do not say how high the bar is. So make the standard concrete: SMART (specific, measurable, acceptable, realistic, time-bound).
  • Measuring instrument: the way you measure whether the result meets the standard.

How good is good enough?

When is the project result good enough? Ideas and expectations often diverge on this. This is exactly where things go wrong in many projects: when the result is delivered, it turns out the sponsor expected something completely different. You prevent this by formulating the quality criteria clearly in the definition phase. Quality then means: consistently meeting the explicit agreements with the sponsor about the project result, within boundaries you have discussed and agreed together.

The book Project Driven Creation distinguishes three levels of quality:

  • Required quality: the minimum. If this level is not achieved, the project fails and a serious conflict arises with the sponsor.
  • Expected quality: what the sponsor expects. This is hard to capture in firm agreements and is all about the relationship with the sponsor and other players in the field.
  • Possible quality: includes the other two levels and goes beyond them. It arises when the team members commit themselves personally to what the sponsor wants to achieve with the project. This is the quality that sets the project apart.

Going for gold? Remember that the last bits of extra quality cost a relatively large amount of time and money. If you do not know the sponsor's quality standard and you have an ambitious team, this can lead to a considerable budget overrun.

How to make the table with the team

  1. List the quality criteria. Make the sponsor's picture concrete. Imagine the end result has been achieved: what do you see? Describe it as if you were looking at a photograph or watching a film. What must have been achieved? Give each criterion a concrete standard.
  2. Prioritise the criteria. First and foremost, the sponsor determines what is important, possibly together with the end users. A handy aid is the quality matrix: plot for each criterion how important it is to the sponsor and how difficult it will be for the team to meet it. This shows at a glance which criteria need extra attention.
  3. Determine the measuring instruments for the most important criteria. These need to be tailored to the project: instruments you use during the execution to measure whether the result will meet the sponsor's wishes and expectations, such as standards, peer review, audits, test panels or pre-testing. The book Project Driven Creation calls them control instruments. Note: many 'quality criteria' in project documents are actually evaluation instruments, for afterwards. What matters is that you can establish before delivery whether the quality is sufficient, and that often requires completely different instruments.
  4. Record the consequences in the plan. Add the table to the project contract, as an appendix or a section. You will probably also need to adjust other parts, such as the project definition, the activity plan and the schedule: when making the table you often come across activities that are not yet included. Also translate extra work into the schedule and the budget.

If you fill in the table together, you also often see that the results in the project definition can be sharpened a little further.

Tips

  • Involve the users of the project result when formulating the quality criteria.
  • Make it clear that, in principle, you will not deliver anything that has not been agreed. And remember that new ideas about quality during the execution usually have consequences for budget and schedule.
  • Limit yourself to the criteria that really matter. Too many criteria obscure what it is all about.
  • Check with the people involved whether they find the criteria relevant and feasible.

Where does the quality table fit?

  • In the project definition. There, quality is one of the constraints: what requirements does the sponsor set for the result? The quality table works out those requirements.
  • In the project contract. In the control plan you describe quality as a set of requirements for the result and/or quality requirements for the process. The quality table describes this in more detail. It is often a separate appendix to the plan; the project contract template also includes it as an appendix.
  • Later in the definition phase. Making a quality table together with the team is a useful activity. In practice you do this later in the definition phase, once the activity plan has been made. See above for how to do it.
  • Before delivery. Before delivery you test the results and subdeliverables against the standards. See also Closing a project.