PDC · the risks

Risk Management

What can go wrong, and what could cause it? With the whole team you go through the activity plan looking for obstacles ahead. Everyone first writes down the risks on their own; then you decide together which risks to act on. For those, you come up with measures in small groups, with who and when, and you put them straight into the activity plan.

The presentation screen · Risk Management
Where in PDC
After the activity plan, to check the project contract; again later, when you review the risks
With whom
The project team
How long
About an hour and a half
Output
Risk analysis (Excel, PDF, image), the updated activity plan (Excel, PDF, progress file)

Why together?

With a risk analysis you check and strengthen the project contract, manage expectations and stay alert as a team. If you do it together, everyone brings in their own knowledge of the plan, and the whole team knows which risks you act on and who does what. With Sessions everyone first writes on their own, in silence. So the first or loudest voice doesn’t decide which risks end up on the table.

The project contract as a pyramid: WHAT (project definition), HOW (activity plan), WITH WHAT (control plan) and WHAT IF (risk analysis)
The risk analysis is the WHAT IF of the project contract: that is how you check and strengthen it.

How the session runs

A video of just over a minute, with sound. How a team maps out the project’s risks together in Sessions.
The presentation screen at Opening
Everyone joins

Opening

Everyone joins, preferably on a laptop. The facilitator puts the explanation on the screen: why you are doing a risk analysis, an example of a risk and the risk matrix. Likelihood goes to the right, impact upwards. Above the line you act on the risk with measures; below it you monitor.

A team member’s laptop at Identifying risks
Everyone thinks first

Identifying risks

Everyone writes down the risks in silence, one at a time: first the cause (what could cause it), then the consequence (what goes wrong). For example: “Because local residents object, the permit comes too late.” Team members open the activity plan and the project definition alongside. Everyone sees only their own risks.

The presentation screen at Prioritising
Visible together

Prioritising

Taking turns, someone puts a risk on the table. First you clarify it; whoever has something similar adds it. Then the person who brought it in places it in the risk matrix. In doubt? Ask: do we need to do something about this? Every placed risk gets a number: R1, R2 … Next to the risk matrix everyone sees the risks in order of priority.

A group’s laptop at Measures
Wording it in small groups

Measures

In fixed groups you come up with measures for the risks above the line: reduce, avert or transfer. For each measure: what, who and when, concrete and with an owner. Each group works on one laptop; the measure appears as a draft on the schedule.

The presentation screen at Deciding
Deciding together

Deciding

Each group reports back, and together you adjust. Then you put the measures into the activity plan, with the label of their risk. Finally everyone moves cards at the same time until the schedule fits.

The output at The result
Tested and recorded

The result

You download the risk analysis as an Excel file, as a PDF (the risk matrix with a table alongside, the list of risks and the plan) or as an image. You download the updated activity plan as an Excel file, as a PDF and as a progress file for Activity Plan.

What does a session cost?

One start code is good for one session with this format. You receive it by email within two working days. With the example in the format you practise first, without using up the code.

€150 per session

Excluding VAT.

Good to know

  • You don’t have to start from scratch: you build on the activity plan from Activity Plan. The clusters, the activities, the timeline, the project definition and the agreements come along. Is the plan in another file? Then you use your organisation’s own AI tool.
  • No plan yet? That works too: the measures then form a new plan.
  • Already have a list of risks? You bring it in in one go: every line becomes a risk.
  • You put the moment when you review the risks straight into the schedule, as a meeting.
  • At a follow-up meeting you continue from the progress file you saved: the risks, their place in the risk matrix and the measures in the plan are still there. When prioritising you see the previous priority alongside.
  • Also in English, for international teams.

Risk Management with your own team?

We use Sessions in our own facilitation. Would you like to use it yourself, as a project leader, programme manager, facilitator or for a whole organisation? Try it out once with your own team, or ask us about the options.